Project Phasing

 

The following table indicates the tentative phasing of the project:-

 

a) WDFC

 

SN Sections Targets
1. Ateli-Phulera  (190 Km) August 18 (completed)
2. Rewari-Madar (306 Km) December - 18
3. Madar Marwar (128 km) February 2019
4. Marwar-Palanpur (207 Km) September- 19
5 Palanpur-Makarpura (308 Km) March -20
6. Makarpura- JNPT (430 Km) March - 20
7. Rewari – Dadri (127 Km) March -20
 
b) EDFC

 

SN Section Target
1. Khurja-Bhadan (200 km) November- 2018
2. Bhadan-Bhaupur (143 Km) January-2019
3. Bhaupur-Mughalsarai (402 km) August-2019
4. Sonnagar – Mughalsarai (126 km) October- 2019
5 Khurja-Dadri (46 km) December-2019
6. Pilkhani – Sahnewal (179 km) March -20
7. Khurja – Pilkhani (222 km) March -20